Refinery Agreement signed

BPGIC entered into a refinery agreement with its Phase I off take customer, Al Brooge International Advisory LLC (“BIA”). The Refinery Agreement provides that the parties will use their best efforts to finalize the technical and design feasibility studies for a refinery with a capacity of 25,000 bpd to be…Read More

Land Lease Signed With FOIZ

BPGIC signed a land lease agreement with Fujairah Oil Industrial Zone (FOIZ) for a strategically located and prime plot of land with a total area of approximately 450,000 m2 on which BPGIC plans to develop its Phase III facility. BPGIC expects that Phase III alone could add storage and services capacity…Read More

Technical Studies Announced

The studies, which are expected to be completed within three months, will develop all necessary technical definition, cost and schedule estimates for the proposed Phase III facility. Brooge Energy believes that, upon completion, the Phase III facility can add an additional storage capacity ranging from 2,100,000 m3 up to 3,500,000 m3 of…Read More

Completion of Basic Designs of Phase 3

In April 2020, the Company appointed MUC Oil & Gas Engineering Consultancy to complete the basic design and Front End Engineering Design (FEED) study for its planned 180,000 bpd refinery and the Phase III oil storage facility in Fujairah, UAE. Completing the basic design progresses the Company’s plan to develop…Read More

Field Environment Impact Assessment

Starting of Preconstruction works

The preconstruction work includes the commencement of the Soil Investigation and the Environmental Impact Assessment (“EIA”) report. These are major milestones that pave the way for construction to start on the Phase III oil storage facility in Fujairah, UAE, which is expected to be operational in late 2022. Upon completion,…Read More

Soil Investigation

The preconstruction work includes the commencement of the Soil Investigation and the Environmental Impact Assessment (“EIA”) report. These are major milestones that pave the way for construction to start on the Phase III oil storage facility in Fujairah, UAE, which is expected to be operational in late 2022. Upon completion,…Read More

Environment Impact Assessment Study Submission

24.12.2020Soil Investigation